Tiger Resources revises mining schedule as copper stockpile rises

Tiger Resources has revised its mining schedule at the Kipoi Copper project in the Democratic Republic of Congo (DRC) as ore stockpiled rises in September

“With three months of ore on the ROM stockpile available as plant feed, we have decided to reduce the rate of ore mining and increase the waste mined,” Tiger md Brad Marwood said. “This will help us to ensure that Stage 2 of the Kipoi central pit is mined down to the ore-bearing material by August 2012, when mining of Stage 1 of the pit is planned to finish,”...