Trevali’s Caribou mill commissioning on target

Trevali Mining Corp’s ramp-up of its Caribou zinc-lead-copper-precious metals project in the Bathurst Mining Camp in northeastern New Brunswick, Canada, is progressing on schedule, recently surpassing 50% of nameplate production capacity.

Underground mining has resulted in a mill-feed stockpile of about 110,000 tonnes, and underground dewatering and refurbishment are on target to be completed in August and October, respectively, Trevali said. The semi-autogenous grinding mill’s circuits are now integrated and functional, with daily throughput of 1,500 tpd...

Published

This article was first published by AMM

July 08, 2015

02:01 GMT